Hiding non-working time in MS Project

Hiding non-working time in MS Project

How can one hide the non working time in MS Project? I mean I want the calendar zone of the gant chart not to display weekends and holidays. Is this possible?

Asked by: Guest | Views: 288
Total answers/comments: 2
Guest [Entry]

"You cannot hide the display of Saturday and Sunday in the Gantt chart view. You can
show a ""5 day"" week in the Calendar view."
Guest [Entry]

"It it not possible to omit the weekends; however, you may right-click on the Gantt Chart and choose Non-working Time... > Formatting options > Draw: In front of task bars.

This essentially covers up the weekend portions of the task bars.

This only makes a difference when you are zoomed in on the Gantt Chart; when you zoom out it doesn't make a difference. I keep hoping that Microsoft will add a feature to omit the weekends from the Gantt Chart view, or that someone will create an add-in to do this. This would be the greatest add-in."